| Project | Round-trip transit of bulk cargo transportation from Mongolia | Duration of transportation | July 19, 2013 to September 10, 2013 |
| Means of transportation | Transit automobile transportation | Place of dispatch | Erenhot |
| Place of destination | Davao, Philippines | Total volume of transportation | 15 vehicles |
| Distance of transportation | Over 800 km | Description of cargoes | Zoomlion QUY650 tower crane |
| Processes & Procedures | |||
Transferring the cargoes to medium-sized vehicles at Erenhot, transit customs declaration at Erenhot, transporting the cargoes via vehicles to Tianjin Port, transit customs clearance at Tianjin Port, unloading the bulk cargoes to the wharf of the No. 4 Company, and the containers were sent to Tianjin Binhai COSCO Container Logistics Co., Ltd, container gate-in, and handling of the cargoes in the presence of the customer.
| |||
| |||